Due to open mid 2015 the Len Lye Centre in New Plymouth is well underway.
Progress so far:
Progress so far:
- The stainless steel for the façade has arrived from Japan
- The moulds for the shaping of the stainless façade have been made and tested
- Second story precast walls are being put in place
To come:
- The construction of a steel frame work to support the pre-cast exterior wall that will in turn be covered by the shaped mirror surface stainless steel.
You can read a more complete report of progress here